Using the problem stated in the Special window, Calculate the expected value of duration (
Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A . 8
B . 8.8
C . 9.1
D . 9.7
E . 10.5