第1题
第2题
A.they come from the same source
B.they are correlated with one central meaning
C.they are listed under one headword in a dictionary
D.all the above
第3题
A、 they come from the same source
B、 they are correlated with one central meaning
C、 they are listed under one headword in a dictionary
D、 all the above
第4题
What is this report mainly about?
A.Phone inquires about hotel bookings for the 2008 Olympic Games.
B.Beijing Hotel is one of the most top hotels in the capital.
C.Beijing will host the 2008 Olympic Games.
D.Visitors from all over the world will come to China for the games.
第5题
A.The criticisms have been increasing
B.The criticisms may not be well justified sometimes
C.The criticisms mainly focus on the quality of non-university programs
D.The criticisms usually come from advocacy groups and so-called educational entrepreneurs
第6题
A、many new migrants are unskilled workers
B、many new migrants are not used to the Australian way of life
C、many new migrants come from the non-English-speaking world
D、many new migrants feel rejected in Australia
第7题
In preparing a good project definition, experienced project managers will:
AConcentrate mainly on the end product rather than costs or benefits. These come later.
BRealize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.
CUnderstand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
DTry to convert objectives into quantifiable terms.
EAll of the above
第8题
179 In preparing a good project definition, experienced project managers will:
A. Concentrate mainly on the end product rather than costs or benefits. These come later.
B. Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.
C. Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
D. Try to convert objectives into quantifiable terms.
E. All of the above
第9题
97 In preparing a good project definition, experienced project managers will:
A. Concentrate mainly on the end product rather than costs or benefits. These come later.
B. Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.
C. Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
D. Try to convert objectives into quantifiable terms.
E. All of the above
第10题
Lexicographers see homonyms as unrelated in sense. ()