23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第2题
Translate the sentence into Chinese.
Estimates of the number of homeless Americans range from 350,000 to three million.
第3题
165 Budgetary estimates are the output of the _____ phase(s) of the project.
A. conceptual
B. development
C. implementation
D. finish
E. All of the above
第4题
We are looking _______ estimates to recover the seats in our two main cinemas.
A、forward
B、for
C、into
D、after
第5题
A.budget
B.plan
C.risk
D.contract
第6题
A. low salvage value estimates and long average lives.
B. high salvage value estimates and long average lives.
C. high salvage value estimates and short average lives.
第7题
● A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
A 4 weeks
B 5 weeks
C 6 weeks
D 7 weeks
E None of the above.
第8题
19 Parametric cost estimating involves
A. using the WBS to do bottom up estimates
B. defining the perimeters of the life-cycle
C. calculating the individual estimates of work packages
D. using a statistical model to estimate costs
E. A and C
第9题
Budgetary estimates are the output of the _____ phase(s) of the project.
A . conceptual
B . development
C . implementation
D . finish
E . All of the above.